EastLink/Seaford

Key features

  • EastLink Interchange under Peninsula Link
  • Lathams Road over Peninsula Link
  • Peninsula Link over Dandenong-Frankston Road
  • Entry and exit ramps (northbound and southbound)
  • Ballarto Road over Peninsula Link
  • Major artwork

Notifications

Asphalting Frankston-Dandenong Road to Ballarto Road

Construction program

This is an indicative program only and dates and sequence of events may change as the project progresses.

EastLink bridges and ramp construction
Ongoing to August 2012

Bulk earthworks
Ongoing to July 2012

Freeway bridge over Frankston-Dandenong Road
Ongoing to February 2012

Freeway roadworks
March 2011 - April 2012

Noise walls, lighting, barriers, gantries, traffic lights, linemarking, signs 
April - July  2012

Vegetation planting
August - September 2012

Asphalting
September - October 2012