Key Features
- Peninsula Link an elevated structure through The Pines Flora and Fauna Reserve
- Skye Road over Peninsula Link
- On- and off- ramps
- Key environmental management features
- Minor art works at Skye Road
Construction program
This is an indicative program only and dates and sequence of events may change as the project progresses.
Bulk Earthworks
Ongoing until March 2012
Ballarto Road bridge construction
Ongoing until June 2012
The Pines fauna crossing
Ongoing until August 2012
Skye Road bridge construction
Ongoing unrtil April 2012
Roadworks
October 2011 - April 2012
Noise walls, lighting, barriers, gantries, traffic lights, linemarking, signs
April - July 2012
Vegetation planting
August - September 2012
Asphalting
September - October 2012