The Pines

Key Features

  • Peninsula Link an elevated structure through The Pines Flora and Fauna Reserve
  • Skye Road over Peninsula Link
  • On- and off- ramps
  • Key environmental management features
  • Minor art works at Skye Road

Construction program

This is an indicative program only and dates and sequence of events may change as the project progresses.

Bulk Earthworks
Ongoing until March 2012

Ballarto Road bridge construction
Ongoing until June 2012

The Pines fauna crossing
Ongoing until August 2012

Skye Road bridge construction
Ongoing unrtil April 2012

Roadworks
October 2011 - April 2012

Noise walls, lighting, barriers, gantries, traffic lights, linemarking, signs 
April - July  2012

Vegetation planting
August - September 2012

Asphalting
September - October 2012