Key Features
- Eramosa Road West overpass over freeway.
- Bungower Road Interchange overpass over freeway.
- Land forming at Bungower Road.
- Mornington-Tyabb Road Interchange.
- Sensitive water way management.
Construction Program
This is an indicative program only and dates and sequence of events may change as the project progresses.
Freeway bridge over Mornington Railway Line
Ongoing until March 2012
Mornington Tyabb Road bridge over freeway
Ongoing until March 2012
Freeway bridge over Balcombe Creek
Ongoing until early 2012
Eramosa Road bridge over freeway
Ongoing until March 2012
Roadworks
October 2011 - April 2012
Noise walls, lighting, barriers, gantries, traffic lights, linemarking, signs
April - July 2012
Vegetation planting
August - September 2012
Asphalting
September - October 2012