Karingal

Key Features

  • Cranbourne Road Interchange.
  • Stony Point Railway Bridge overpass.
  • Willow Road Pedestrian Bridge.
  • The sensitive Westerfield property. 

Construction Program

This is an indicative program only and dates and sequence of events may change as the project progresses.

Stony Point Rail Bridge
Complete

Cranbourne Road bridge over freeway
Ongoing until May 2012

Willow Road pedestrian bridge
Ongoing until March 2012

Bulk Earthworks
Ongoing until February 2012

Roadworks 
September 2011 - April 2012

Noise walls, lighting, barriers, gantries, traffic lights, linemarking, signs 
April - July  2012

Vegetation planting
August - September 2012

Asphalting
September - October 2012 