Devilbend

Key Features

  • Loders Road overpass over freeway. 
  • Derril Road underpass.
  • Mornington Peninsula Freeway Interchange. 
  • Sensitive water way management.

Construction Program

This is an indicative program only and dates and sequence of events may change as the project progresses.

Freeway bridges over Devil Bend Creek
Ongoing until February 2012

Bulk Earthworks
Ongoing until early 2012

Loders Road bridge over freeway
Ongoing until May 2012

Freeway bridge over Moorooduc Highway
Ongoing until early 2012

Roadworks
August 2011 - April 2012

Noise walls, lighting, barriers, gantries, traffic lights, linemarking, signs 
April - July  2012

Vegetation planting
August - September 2012

Asphalting
September - October 2012 